Level space and commercial quays sheltered by Botafoc Breakwater at Ibiza Port
Ibiza
Location: Ibiza (Spain)
Developer: Port Authority of the Balearic Islands
Budget: 70.927.558,75 €
Execution time: 37,5 months
Characteristics
Construction of a new quay 487 ml. long, with 11 reinforced concrete floating caissons. Forming an esplanade of 60,125 m2 limited by Botafoc’s Dock, the new quay wall and a rubble-mound breakwater. Execution of two jettys, 200 ml. long, and 30 m width. Concrete deck slab formed by beams and upper slab, founded over reinforced concrete piles.
The key figures of the works are:
Caissons quay wall: 987 ml
Dredging: 484.634 m3
Rubble mound bedding layer, riprap: 180.000 t.
Concrete floating caissons: 11 uds
5 ud. Length – 41,7 ml, Beam – 13,97 ml, Depth –
11,60 ml
6 ud. Length – 41,7 ml, Beam – 15,27 ml, Depth –
17,50 ml
Concrete in caissons: 19.429 m3
Steel reinforcement in caissons: 1.687.571 Kg
Rock backfilling caissons wall: 125.000
Capping beam concrete: 8.752 m3
Capping beam steel reinforcement: 369.965 Kg
Land esplanade: 60.125 m2
Granular filling: 518.052 m3
Pre-load mobile dune
Pavements, facilities and perimeter access
Transversal quays 2 x 200 ml
Piles: 304 ud / 11.315 ml
Design Optimization with Ostererg’s cells
Steel reinforcement in piles: 2.060.422 Kg
Concrete on deck slab: 12.523 m3
Steel reinforcement on deck slab: 2.403.175 Kg
Home > Proyects > Docking and Mooring Works > Level space and commercial quays sheltered by Botafoc Breakwater at Ibiza Port
The Docking and Mooring Works, the so-called Wharves, allow ships or vessels to approach in the protected area between land and sea to carry out port activities, such as loading and unloading goods, and passenger and provisions transport, among others.
View all
Level space and commercial quays sheltered by Botafoc Breakwater at Ibiza Port
Ibiza

Southern Quay of the Southern Dock of the Sagunto Port
Valencia

Quay Prat construction, Barcelona Port, Phase I
Barcelona

Bulk Cargo Terminal Infrastructure, Phase I
Ploce (Croacia)

Modernization works of Solid Bulk Terminal of Puerto Cortes, Honduras
Puerto Cortés

Berth for large vessels at the docks of Poniente. Palma de Mallorca
Mallorca

Cruise dock in the Port of Valencia Extension, Phase I
Valencia

Western Quay southern stretch Sagunto Port extension
Valencia

Strengthening and upgrading of the first section of Muelle de Levante in the Port of Valencia
Valencia

Valencia Port Inner Dock Customs Quay widening (America’s Cup 2007)Valencia Port Inner Dock Customs Quay widening (America’s Cup 2007)
Valencia

Lineal quay in north shore of Gandía Port. “Los Borgia” quay
Valencia