Quay Prat construction, Barcelona Port, Phase I
Barcelona
Location: Barcelona (Spain)
Developer: Port Authority of Barcelona
Budget: 57.541.028,12 €
Execution time: 14 months
Characteristics
Construction of a 1,000 m long quay with 16 m of minimum depth, formed by reinforced concrete caissons, creating an area of 81 Ha, where the rock behind quay wall is included, as also the filling of some adjoining enclosures.The product of those fillings is obtained from the dredge of the caissons’ trench and the boats manoeuvre area.
The key figures of the works are:
Dredging: 5.287.187 m3
Dredging granular filling: 386.344 m3
Rubble mound bedding layer and breakwaters, riprap: 2.218.500 t
Reinforced concrete floating caissons: 25 uts.
Home > Proyects > Docking and Mooring Works > Quay Prat construction, Barcelona Port, Phase I
The Docking and Mooring Works, the so-called Wharves, allow ships or vessels to approach in the protected area between land and sea to carry out port activities, such as loading and unloading goods, and passenger and provisions transport, among others.
View all
Level space and commercial quays sheltered by Botafoc Breakwater at Ibiza Port
Ibiza

Southern Quay of the Southern Dock of the Sagunto Port
Valencia

Quay Prat construction, Barcelona Port, Phase I
Barcelona

Bulk Cargo Terminal Infrastructure, Phase I
Ploce (Croacia)

Modernization works of Solid Bulk Terminal of Puerto Cortes, Honduras
Puerto Cortés

Berth for large vessels at the docks of Poniente. Palma de Mallorca
Mallorca

Cruise dock in the Port of Valencia Extension, Phase I
Valencia

Western Quay southern stretch Sagunto Port extension
Valencia

Strengthening and upgrading of the first section of Muelle de Levante in the Port of Valencia
Valencia

Valencia Port Inner Dock Customs Quay widening (America’s Cup 2007)Valencia Port Inner Dock Customs Quay widening (America’s Cup 2007)
Valencia

Lineal quay in north shore of Gandía Port. “Los Borgia” quay
Valencia