Prat Quay rehabilitation – Barcelona Port
Barcelona
Location: Barcelona (Spain)
Developer: Port Authority of Barcelona
Budget: 62.999.020,30 €
Execution time: 27 months
Characteristics
Reconstruction of 660 m from de mooring line of caissons quay, after the incident occurred on the first of January 2007, completing 93 Ha of an area will house the new Container Terminar of the Barcelona Port.
The key figures of the works are:
Dredging of material on top of existing rubble mound bedding layer and cleaning of 3 m of upper layer: 1.176.432 m3
Basin General Dredging: 2.787.622 m3
Granular filling dredging: 970.125 m3
Rubble mound bedding layer and containing dikes, riprap: 902.656 t
Refloating and repairing of 11 displaced concrete caissons by means of chimneys as cells extension
5 non-refloating concrete caissons demolition and manufacture of 5 new ones